Kano Peri-urban Electrification Phase II
Kano State · in progress · official record
2.2k · following
Wikimedia Commons — Lagos aerial
Grid extension and transformer installation for peri-urban communities around Kano.
Work progress
55%
Funding received
38%
55% work · 38% funded
₦7.50bn still unreleased vs budget
Field media
Citizen and official photos and video attached to this project.
3 items
Work progress
Where the project sits on the delivery path — funding is tracked separately below.
- 01
planned
Reached
- 02
started
Reached
- 03
in progress
Now
- 04
completed
Ahead
Record timeline
Work status, funding, spend, evidence, reports and memory — newest first.
12 events
- Citizen report · New transformer installed but not energised
Community received a transformer months ago; still no supply.
report
- Work status · in progress
Partial energisation of first corridors
status
- Spend recorded · ₦1.40bn
contractor — Northern Grid Partners — corridor energisation
spend
- Funding received · ₦2.00bn
Federal power capital — second tranche via budget release
funding
- Spend recorded · ₦1.80bn
contractor — Northern Grid Partners — poles & transformers
spend
- Work status · started
Pole erection commenced
status
- Funding received · ₦2.50bn
Federal power capital release via budget release
funding
- Contract awarded · ₦10.80bn
Contract: Kano Peri-urban Electrification Phase II — Northern Grid Partners Ltd
contract
- Work status · planned
Programme design
status
Budget & funding
How much was meant to arrive, what landed, and what was spent.
Federal Capital Budget 2024 — Power
Source mix (received)
- government budget₦4.50bn
Funding sources
- ₦4.50bn / ₦12.00bn
Contract: Contract: Kano Peri-urban Electrification Phase II · Northern Grid Partners Ltd · ₦10.80bn · active
Open full money trail →Income stream
Money arriving — releases, grants, donations.
2024-10-05
Federal power capital — second tranche
budget release₦2.00bn
Official Record2024-03-20
Federal power capital release
budget release · linked source₦2.50bn
Official Record
Spend record
Where money went — materials, labour, contractors.
₦1.40bn
Official Record₦1.80bn
Official Record
Relationships
Evidence
Short clip along a newly energised stretch. Demo media for the public record.
Concrete pad prepared for a distribution transformer on the peri-urban corridor.
Pole erection on Phase II electrification corridor.
Citizen reports & official responses
Community received a transformer months ago; still no supply.
ReportedHistory / political memory
No timeline events yet.
Follow the thread
Move between connected records in the public graph.
1 steps
- 1← federal oversightBola Ahmed Tinubu
Sources
- Citizen photo set — Allen Avenue spur (2025)Community contributors · 2025-08-03
- Citizen photo set — Allen Avenue spur (2025)Community contributors · 2025-08-03
- Citizen photo set — Allen Avenue spur (2025)Community contributors · 2025-08-03
Community
Public contributions
Arguments, polls, pages, comments, and social pointers about Kano Peri-urban Electrification Phase II. Community content is not platform verification or a court finding.