Project

Allen Avenue Spur Rehabilitation

Allen Avenue Ward · abandoned · official record

3.9k · following

Wikimedia Commons — Bad road in Lagos

Rehabilitation of a 1.8km spur off Allen Avenue including drainage, asphalt overlay and sidewalk repairs. Construction began, then stalled. Citizen reports and official responses form the signature Follow-the-Thread demonstration.

At a glance· Allen Avenue WardabandonedPartially funded
Funding request · GoFundMe

Work progress

42%

Funding received

41%

Field media

Citizen and official photos and video attached to this project.

2 items

Work progress

Where the project sits on the delivery path — funding is tracked separately below.

  1. 01

    planned

    Reached

  2. 02

    started

    Reached

  3. 03

    in progress

    Now

  4. 04

    completed

    Ahead

Branch · abandoned

Work left the main path — see timeline for the recorded reason.

Record timeline

Work status, funding, spend, evidence, reports and memory — newest first.

22 events

  1. Official response published

    The Ministry acknowledges delay on the Allen Avenue spur. Works paused pending resolution of a materials and payment dispute with the contractor. A revised mobi…

    response

  2. Record · Outcome

    As of the latest record, the project remains incomplete. Funding gap and works pause are preserved in political memory.

    memory

  3. Citizen report · Road abandoned for months — Allen Avenue spur

    This road has been abandoned for over two years of calendar delay from the expected end date. No workers on site. Dangerous for vehicles and pedestrians after rain.

    report

  4. Funding received · ₦22.6m

    Community donors (GoFundMe batch) via gofundme

    funding

  5. Work status · abandoned

    No visible works for 90+ days; community reports

    status

  6. Work status · delayed

    Payment and materials dispute reported

    status

  7. Spend recorded · ₦150.0m

    labour — Site labour — disputed final certificate. Payment dispute reported; works stalled thereafter.

    spend

  8. Spend recorded · ₦720.0m

    materials — Asphalt & aggregate suppliers (via contractor)

    spend

  9. Work status · in progress

    Base course laid on 40% of stretch

    status

  10. Funding received · ₦900.0m

    Lagos Ministry of Works — second release via budget release

    funding

  11. Spend recorded · ₦980.0m

    contractor — Delta Roads Nigeria Ltd — mobilisation & base course

    spend

  12. Funding received · ₦12.0m

    Civic Track Nigeria programme fund via bank transfer

    funding

  13. Work status · started

    Site handover

    status

  14. Record · Project Start

    Site handover and start of Allen Avenue spur rehabilitation.

    memory

  15. Funding received · ₦1.20bn

    Lagos Ministry of Works — first release via budget release

    funding

  16. Contract awarded · ₦4.85bn

    Contract: Allen Avenue Spur Rehabilitation — Delta Roads Nigeria Ltd

    contract

  17. Work status · planned

    Included in capital programme

    status

Funding request

Public donation or community ask linked to this project.

GoFundMeopen

Complete Allen Avenue spur — community materials fund

Government release stalled. This community ask covers asphalt patching materials while the contractor dispute is resolved — demo campaign.

Hosted by Civic Track Nigeria

₦22.6m raisedof ₦85.0m · 27%
Open on GoFundMe (external)

Budget & funding

How much was meant to arrive, what landed, and what was spent.

Partially funded41% of budget received
Budget target₦5.20bn
Received₦2.13bn
Spent₦1.85bn

Lagos State Capital Budget 2024 + Federal counterpart support line

Source mix (received)

  • government budget₦2.10bn
  • ngo grant₦12.0m

Funding sources

  • government budget
    Lagos State Capital Budget 2024 — Works

    Approved allocation; ₦3.1bn still unreleased.

    ₦2.10bn / ₦5.20bn
  • ngo grant
    Civic Track Nigeria — monitoring grant (in-kind programme)

    Programme spend for community monitors, not construction cash.

    ₦12.0m / ₦12.0m

₦3.1bn of the approved allocation has not been released. The public record shows funding approved but incomplete cash backing.

Contract: Contract: Allen Avenue Spur Rehabilitation · Delta Roads Nigeria Ltd · ₦4.85bn · active disputed

Open full money trail →

Income stream

Money arriving — releases, grants, donations.

  • 2025-06-15

    Community donors (GoFundMe batch)

    gofundme

    ₦22.6m

    Reported
  • 2024-09-01

    Lagos Ministry of Works — second release

    budget release

    ₦900.0m

    Official Record
  • 2024-08-01

    Civic Track Nigeria programme fund

    bank transfer

    ₦12.0m

    Reported
  • 2024-06-15

    Lagos Ministry of Works — first release

    budget release · linked source

    ₦1.20bn

    Official Record

Spend record

Where money went — materials, labour, contractors.

  • 2025-01-05

    Site labour — disputed final certificate

    Payment dispute reported; works stalled thereafter.

    ₦150.0m

    Disputed
  • 2024-11-01

    Asphalt & aggregate suppliers (via contractor)

    ₦720.0m

    Reported
  • 2024-08-15

    Delta Roads Nigeria Ltd — mobilisation & base course

    ₦980.0m

    Official Record

Relationships

Evidence

Citizen reports & official responses

Road abandoned for months — Allen Avenue spur

This road has been abandoned for over two years of calendar delay from the expected end date. No workers on site. Dangerous for vehicles and pedestrians after rain.

Reported
Official response

The Ministry acknowledges delay on the Allen Avenue spur. Works paused pending resolution of a materials and payment dispute with the contractor. A revised mobilisation plan is under review. Citizens are encouraged to continue documenting conditions.

2025-09-01

History / political memory

  1. Project Start

    Site handover and start of Allen Avenue spur rehabilitation.

  2. Outcome

    As of the latest record, the project remains incomplete. Funding gap and works pause are preserved in political memory.

Follow the thread

Move between connected records in the public graph.

9 steps

  1. 1
  2. 2
  3. 3
    office holder
    Engr. Tunde Adebayo
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9

Sources

  • Citizen photo set — Allen Avenue spur (2025)
    Community contributors · 2025-08-03
  • Citizen photo set — Allen Avenue spur (2025)
    Community contributors · 2025-08-03
  • Lagos State Official Gazette — Contract Awards Q2 2024
    Lagos State Ministry of Works & Infrastructure · 2024-06-12
  • Federal Capital Budget 2024 — Works & Housing Excerpt
    Budget Office of the Federation · 2024-01-15

Community

Public contributions

Arguments, polls, pages, comments, and social pointers about Allen Avenue Spur Rehabilitation. Community content is not platform verification or a court finding.

Loading contributions…